At 08:38 AM 2/20/2002 +0300, Isaac KASANA wrote:
>Charles,
>Hear are some 1 pence suggestions:
>
>a) Why don't we just ask the building manager and we ran a 1.2KVA supply
>line to the roof with about 8 socket outlets? This should be quite easy
>and not
>so expensive.
I put across a suggestion that we put a switch at the top. what I had in mind
was to have this switch in UCC's NOC(already has stable power). this will be
a temporary measure as we find a lasting solution like what you have
suggested, or even constructing a cage to h'se equipment at the rooftop.
on reflection, the Technical Guidelines require that individual members
deliver
their link to the IXP switch. maybe we shouldn't apply this in its strictness
as this will delay roll out.
>b) If conduits are to be used, they should be metallic and properly earthed
>to the lightening protection line.
good point. we'll take this up with NCR.